Material Quantity, Rate Analysis & Cost Breakdown for Building Construction
However, there are usually three things to consider in the estimation: 1) Volume 2) Area 3) Length. Below is a comprehensive guide to material quantities, rates, and cost breakdowns for building construction.
📐 Volume-Based Estimation
Volume is usually calculated for:
A. Excavation or filling of soil
B. Concrete (Cement Concrete, R.C.C.)
C. Brick work (except brick soling)
D. Woodwork
📏 Area-Based Estimation
Area which has to be calculated:
A. White wash
B. Color work
C. Brick walling
D. Plastering
E. Damp proof course
📏 Length-Based Estimation (Rod / Reinforcement)
Length of hook = 12 × diameter of rod = 12d
Considering 45° crank, additional rod for crank = 0.42 × effective depth = 0.42d
Lapping length: a) Compression = 45d, b) Tension = 60d
📊 Reinforcement Bar Weight per Meter
Diameter (mm)
Weight per meter (kg)
Cross Sectional Area (sq cm)
6 mm
0.222
0.283
8 mm
0.395
0.503
10 mm
0.616
0.785
12 mm
0.888
1.131
14 mm
1.208
1.539
16 mm
1.579
2.011
18 mm
2.000
2.545
20 mm
2.466
3.142
22 mm
2.983
3.801
25 mm
2.854
3.909
28 mm
4.835
6.158
32 mm
6.313
8.042
🧱 Material Quantity for 100 cft R.C.C (1:2:4 Ratio)
🏠 Plinth Area Rates (P.W.D Schedule, 1997) – per sq.m plinth area
Building Type
Foundation Rate (Rs.)
Superstructure Rate (Rs.)
1st floor building
1510
3880
2 storey building
1685
4740
3 storey building
1870
4860
4 storey building
2160
4980
5 storey building
2430
5280
💰 Percentage Cost Breakdown of a House
Foundation cost (up to plinth) – 20%
Superstructure – 80%
Consultant Fee (Design & Supervision) – 3%
Water Supply & Sanitary – 2%
Electricity – 2%
Gas – 3%
Construction Materials – 55%
Labor – 20%
Contractor's Allowance – 10%
Miscellaneous – 5%
📋 Sample Cost Calculation (Total = 50,00,000/-)
Item
Percentage
Amount (Rs.)
Consultant fee design
2.5%
1,25,000/-
Supervision expenses
0.5%
25,000/-
Construction materials
55%
27,50,000/-
Labor cost
20%
10,00,000/-
Water supply
2%
1,00,000/-
Electricity cost
2%
1,00,000/-
Gas cost
3%
1,50,000/-
Contractor profit
10%
5,00,000/-
Miscellaneous
5%
2,50,000/-
Total
100%
50,00,000/-
👷 Labor Rates (Mason's Rate per day)
Labor Type
Rate (Rs./day)
Head Roadmaster / Head Carpenter / Head painter / Head plumber
200
Roadmaster / Carpenter / Painter / Plumber
160
Skilled Helper
120
Skilled labor
100
General labor
80
Skilled Technician
120
Foreman
200
💡 Note: Additional costs for advanced finishing work: Rs. 950 to 1600 per sq.m. Water supply & sanitary works add 15% of total cost. Electrical works add 15% of total cost. Boundary wall 5" brick wall with 8ft interval costs approx Rs. 1.92 per running meter.
🎥 Watch: Construction Estimation & Supervision Tips